Brew Hut Rebuild
Contents
New hut construction
This section documents the effort to rebuild the Brew Hut.
Upcoming Events
Project Tasks
We still need help to do the following:
Completed Project Tasks
- Workhike to build outhouse and clean up garbage July 22-23, 2006
- Build Woodshed / Foundations for stairs / fly out garbage September 2006.
- Build Outhouse July 2006
- Final Workhike (for 2005) workhike October 29-30 to finish the interior and build the deck and stairs
- Remove the old hut We did this on September 24-25 weekend
- Planning-Scheduling - JP
- Prefab Construction - Roland
- Heater - Roland/Jordan
- Foundation - Rueben
- Foundation Layout - Rueben
- Sheet Metal Buying - JP (Temporary)
- Out House Prefab - Bill
- Transport - JP
- Helicopter - JP
- Build the outhouse
Other stuff
Progress Reports
- Brew Hut Minutes October 21 2004
- Brew Hut Minutes February 9, 2005
- Brew Hut Minutes March 1, 2005
- March 7 - Lumber delivered to Roland's
- March 13 - finished cutting joists; cut some studs for walls
- March 20
- March 30 - finished cutting floor insulation; painting floor
- April 4
- April 11
- April 25 - heater delivered, windows started.
- May 02
- May 21 - helicoptered material
- June 12
- June 26 - foundations finished
- July 9 to 17 - the great brew build
- July 30 - the great brew build - part 2
- September 24 - the deconstruction of the old brew hut (brew 2)
- October 29 - final 2005 workhike
New Brew Trail
A new trail is part of the plan for the new hut. See the wiki page for Brew Hut Trail Upgrade