Steps
These are the rough steps needed to layout and build foundations:
- Find a level spot and pick the high corner
- Put in string lines
- Put in first string line (offset from the corner)
- Put in a second string line 90 degrees to the first (use the properties of a 3,4,5 triangle to square it)
- add a "batter" board to the building ends (to tie more stings to)
- measure out distances along lines and mark them with tape to find locations of footings
- put flagging tape on strings so they are not stepped on
- Spray paint the location of the footings
- Dig 6 holes
- Jack hammer a level bottom for the holes if necessary.
- Drill some holes in the rock for rebar
- Put in the footing forms, level them with pegs if needed
- Put in the pier forms (cardboard tubes)
- Attach pegs to the footing forms and mark level on them
- Cut pier forms to length
- Rest pier forms on 2*4's and brace them
- add rebar and other rods
- mix and pour some cement
- vibrate and finish
- place saddles into the piers
- snap a string line in the cement to ensure the piers are straight
Tools needed
Add these to the Tools list (some are already listed on the Foundation page).
- String lines (lots)
- chalk line
- Pegs (salvaged wood from old hut?)
- plumb bob
- hand level
- spray paint
- penciles
- masking tape
- tape measure
- Water level (transparent pipe filled with water, 30 ft long)